If the equipment acts uncoordinated during construction, it will not only affect the work efficiency, but also may cause construction safety accidents. Therefore, once this kind of fault occurs to the excavator, it must be stopped immediately for inspection. The Hitachi zx300-5a deviates when walking, and the composite action is uncoordinated.
Troubleshooting:
Let's first understand this solenoid valve. The main function of the walking straight solenoid valve is to ensure that when the excavator moves in a straight line, when one or more actions of the upper frame's boom and forearm and bucket are operated at the same time, the straight-line walking valve will be opened to ensure the continuity of operation and no deviation
Note: if there is only linear travel without other actions, the travel direct solenoid valve will not be opened, and the hydraulic pump will supply oil to the left and right travel separately
The alarm code of Hitachi zx300-5a is used as a starting point to understand the troubleshooting method for the alarm of walking straight solenoid valve
Fault phenomenon
D032 appears on the display screen. When operating the upper and lower parts of the excavator, the walking linearity cannot be maintained
Troubleshooting process:
Press and hold the buzzer switch, turn the key to on, and enter service diagnosis No.8
Locate the D-3 option
Judgment conditions:
The display screen gives an alarm, and the current value of the proportional valve is more than 1000 ma
Troubleshooting object 1:
If the connectors of other proportional valves are exchanged, D032 disappears. When other alarm codes appear, replace the traveling direct proportional valve (Mark: psv-c)
Troubleshooting object 2:
Check the connecting lines cn-119f and cn-105f between the travel diameter proportional valve and the computer version. Even if the connector is exchanged with the connector of the nearby proportional valve and the start switch is turned on, D032 continues to display. Please check the connecting harness.